KEY FEATURES
We installed the solar plant on a very tight schedule because the client needed to start up its new facility.

HANDLING
Using a mobile crane with a 48 m reach, we were able to position the panels quickly and in complete safety, delivering the modules to central points on the roofs for our team.

CARBON FOOTPRINT
190 tonnes of CO2 saved every year.

  • Completion time

    10 days

  • Location

    Pitched roof