Saracen

Solar PV 121 kWp, solar thermal with 36 collectors

KEY FEATURES
Specially designed reinforced concrete ballast was used, with no drilling of the roof. A rubber mat separates the roof surface from the ballast. A 48-metre crane was needed to lift materials onto the roof, as manoeuvring space was limited.

HANDLING
Using trolleys with rubber wheels, we were able to move the ballast safely across the roof without damaging its surface.

CARBON FOOTPRINT
90 tonnes of CO2 saved every year.

  • Completion time

    12 days

  • Location

    Flat roof